£230,000 resurfacing scheme planned for A29 Carhill Road, Garvagh

Date published: 20 March 2017

A £230,000 major carriageway resurfacing scheme is planned for A29 Carhill Road, Garvagh.

Lane closure during resurfacing work

The resurfacing work extends for a distance of approximately 1.4 kilometres from Magheramore Road south of Garvagh to Lisachrin Road.

The work is expected to commence on Monday 27 March and be substantially completed by Sunday 9 April 2017.

The Department for Infrastructure has carefully programmed the works operations and traffic management arrangements in order to minimise any inconvenience to the public, however, due to the lack of a suitable diversionary route motorists should be aware that some delays may be expected and that additional time should be allowed when planning any journeys.

The above planned dates are subject to favourable weather conditions and the Department will keep the public informed of any change.

For more information about this and other improvement schemes visit: www.trafficwatchni.com